• Home
  • Why Federal Housing Funds Sit Unspent While Wait Lists Grow
Why Federal Housing Funds Sit Unspent While Wait Lists Grow
By Dana Jerlo profile image Dana Jerlo
3 min read

Why Federal Housing Funds Sit Unspent While Wait Lists Grow

Why Federal Housing Funds Sit Unspent While Wait Lists Grow

The Housing Accelerator Fund reached a total of $4.4 billion for new construction across Canada, with Budget 2024 adding $400 million to the program launched in 2023. Two years later, large portions of that allocation remain uncommitted to actual buildings. The money exists. The wait lists are real. The federal government controls the chequebook, but the province controls the legal framework for land use and tenancy, and the municipality controls the permits, when approvals must happen in sequence, a delay at any level compounds.

Federal housing programs operate through a triple-approval system. A developer applying for support through CMHC's Affordable Housing Fund must satisfy federal requirements on unit mix and affordability thresholds. The same project requires separate provincial approval, in Alberta, that means Seniors, Community and Social Services, to access provincial land or additional subsidies. Then municipal permitting follows its own timeline, governed by zoning bylaws, engineering standards, and utility capacity studies. Each layer reviews similar information but requires different formats, and none of the three timelines coordinate.

This is not a complaint about "bureaucrats." It is a description of how the system actually moves money. The federal government controls the chequebook. The province controls the legal framework for land use and tenancy. The municipality controls the permits. When approvals must happen in sequence, a delay at any level compounds. Industry groups tracking Edmonton projects report that the time between concept and first excavation now exceeds 24 months for affordable housing developments, compared to 14-16 months for market-rate projects that skip the federal funding route.

The cost of waiting

Housing construction is capital-intensive. Developers typically borrow against expected timelines. A six-month bureaucratic delay on a $20 million project adds roughly $500,000 in interest carry at current rates, and material costs typically rise during extended approval windows. Federal funds are often allocated as a fixed per-unit subsidy, $150,000 per affordable unit, for instance. When project costs rise during the approval process, the subsidy no longer closes the gap between construction cost and what affordable rents can support. Projects stall or get redesigned, which restarts parts of the approval cycle.

The Housing Accelerator Fund, launched to bypass some of this friction, provides direct federal-to-municipal funding. Edmonton received $175 million under the program, conditional on zoning reforms that would permit up to eight units as of right city-wide. The city passed those reforms in 2024. Money flows only when projects break ground and hit specific completion stages; until then, the allocated dollars do not move even though zoning changes are complete.

Where Edmonton actually removed barriers

Edmonton's Zoning Bylaw Renewal Strategy eliminated the need for site-specific rezoning on most residential parcels. That reform removed one genuine bottleneck: the 8-12 month wait for a rezoning hearing that previously applied to duplexes, townhouses, and secondary suites. The change matters. Small-scale investors adding a legal suite or building a laneway house now avoid the delay that still affects large apartment projects.

But the zoning fix did not eliminate the technical approval stages that follow. Utility connections, stormwater management plans, and engineering reviews still require municipal sign-off, and those departments are processing an unprecedented application volume triggered by the new zoning rules. Administrative capacity has not scaled with the policy change. The bottleneck moved; it did not disappear.

Federal programs also face provincial legislative friction. Alberta's Bill 18, passed in 2024, requires that federal funding agreements touching on provincial jurisdiction be reviewed by the province before taking effect. That adds another approval step between the federal commitment and the municipal project. The rule was designed to protect provincial authority. The effect is another hold point in the sequence.

The structural problem is simpler than it looks. No single entity controls all three approvals. Fixing the federal process does not fix the provincial one. Fixing the provincial process does not accelerate municipal permitting. A project needs all three, in order, and the current average is two years from application to shovel. Every month in that window is a month the allocated money sits while the wait list grows.


Sources

  1. Prime Minister of Canada - Building more homes that Canadians can afford in Edmonton, Alberta - 2024-02-21. https://www.pm.gc.ca/en/news/news-releases/2024/02/21/building-more-homes-canadians-can-afford-edmonton
  2. Canadian Mortgage Trends - Canada needs up to 4.69 million new homes by 2036, but construction could slow: CMHC - 2026-01-01. https://www.canadianmortgagetrends.com/2026/09/canada-needs-up-to-4-69-million-new-homes-by-2036-but-construction-could-slow-cmhc/
  3. CMHC - The Affordable Housing Fund approved $4.4 billion for new construction across Canada in 2024. - 2024-07-15. https://www.cmhc-schl.gc.ca/media-newsroom/news-releases/2024/more-cities-communities-to-access-housing-accelerator-fund